Flagship Hartlepool Waterfront Scheme Faces Axe as Costs Soar to £21.1m...

£11.5m Cost Increase Leaves Hartlepool Waterfront Project on the Brink
22nd Sep 2026
A flagship Hartlepool waterfront regeneration project involving the Museum of Hartlepool and the historic Wingfield Castle is set to be abandoned after estimated costs more than doubled to over £21 million pounds.
Hartlepool Borough Council’s Housing, Growth and Communities Committee will be asked on 30th of September 2026 to endorse a recommendation that the ambitious Tides of Change programme should no longer proceed because of the financial risk it could place on the troubled teesside council which is drowning in millions of pounds of debt.
The project was originally expected to cost around £9.6 million, with plans centred on the redevelopment of the Museum of Hartlepool, restoration of the Wingfield Castle, a maritime heritage programme and wider improvements to the waterfront.
However, detailed design work and condition surveys have since pushed the estimated total cost to be around £21,122,313, with council papers saying that this has created a funding gap of up to around £9.8 million pounds, with no viable solution identified to close it.
Costs more than double
The Tides of Change project was first developed in 2022 as part of the council’s wider Waterfront Programme.
The aim was to secure the future of both the Museum of Hartlepool and Wingfield Castle while transforming the area into a larger visitor attraction alongside the Highlight Active Wellbeing Hub.
The project subsequently secured a £631,440 National Lottery Heritage Fund development grant, based on the original £9.6 million projected cost.
Other funding has also been secured or offeres, which included more than £2.45 million from Arts Council England’s Museum Estate and Development Fund, £218,400 from DCMS/Wolfson and £308,624 offered by the Lloyd’s Register Foundation.
The Arts Council funding was intended to pay for works including roof repairs, insulation, upgraded windows, structural repairs, accessible lifts, new toilets, heating improvements and security measures at the museum.
But despite securing millions of pounds from external sources, the council says the scale of the increase in construction and restoration costs has made the overall project too risky to continue.
Council could have faced almost £10m exposure

The scale of that risk is laid bare in the committee papers, with the current funding schedule identifying a gap of £9,722,820 before a series of proposed or potential funding sources are taken into account.
Those options included a possible £1.5 million uplift from the National Lottery Heritage Fund, additional Tees Valley Combined Authority funding and potentially redirecting £3.4 million originally associated with plans for a Royal Navy Museum development.
Even if all of those sources were agreed, the council says the scheme would still be left with a final programme shortfall of around £1.4 million.
More significantly, the National Lottery Heritage Fund required Hartlepool Borough Council to demonstrate that it was prepared to underwrite any funding gap while other agreements were being finalised.
That could have left the teesside council which in 2023 was declared an authority with no public confidence exposed to almost £9.73 million financial liability, with Hartlepool Borough Council needing to underwrite the full gap of £9,722,820…
Even after potential TVCA funding was secured, the council says it could have remained responsible for any outstanding exposure until other funding became available.
Warning of ‘critical financial position’
Council officers have also reiterated the councils financial position in why the project should now be stopped, with the report stating that the current level of exposure would already represent an “unserviceable liability” for the council, warning that any further increase could place Hartlepool Borough Council in a “critical financial position.”
Officers say the combination of rising construction costs, the remaining funding gap, uncertainty around Wingfield Castle and continuing revenue costs means the overall financial risk has become too great.
That comes against a wider backdrop of acknowledged pressure on council finances.
The report says underwriting such a large and uncertain gap would place additional strain on budgets which are already stretched.
Wingfield Castle proving particularly difficult

A major part of the cost pressure surrounds the historic PS Wingfield Castle, which remains moored alongside the Museum of Hartlepool.
The council has explored a number of options for restoring the vessel and currently believes the most cost-effective solution would involve lifting it onto a cradle beside the quay so repairs could be carried out.
But officers admit there is still no full certainty over either the restoration cost or the amount the council would have to spend maintaining the ship in future.
The report says the Wingfield Castle is contributing “considerably” to the project’s funding problems, although removing the vessel from the scheme would still leave a significant funding gap.
Council papers also warn that without an affordable solution the condition of the Wingfield Castle could continue to deteriorate… & potentially ‘could sink’, creating both a maintenance and environmental problem.
Among the risks formally identified by the authority is the possibility of the vessel sinking if it is not repaired.
Another ambitious regeneration scheme hits financial reality

The figures contained within the September committee papers demonstrate just how dramatically the economics of the project & the finances of Hartlepool Borough Council have fundamentally changed in the space of just 12 months .
What began as a £9.6 million redevelopment has evolved into a scheme costing more than £21.1 million — an increase of around £11.5 million.
The Housing, Growth and Communities Committee is being recommended to formally agree that Tides of Change project should not proceed while instructing officers to look for alternative opportunities for the museum and waterfront site.
That decision is due to be considered when the committee meets at the Civic Centre on 30th September 2026.